True/False
Risks should be identified and documented in a risk register, but should not be included in either a work breakdown structure or a project's timeline map.
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q8: If it became clear that a project
Q9: Team members working on a project will
Q10: When scoping a project, what needs to
Q11: Updating expenditure records is an example of
Q12: Which of the following should a project
Q14: When an activity that is part of
Q15: The loss of support for a project
Q16: The person or persons responsible for guiding
Q17: When stakeholders ask for adjustments to a
Q18: To establish operating guidelines for how a