Multiple Choice
Which of the following should a project manager not do?
A) Monitor the quality of team members' output
B) Provide the resources that people need to achieve their deliverables
C) Monitor the progress and completion of activities and tasks against timelines
D) Undertake activities or tasks that are urgent but not important
E) Pay attention to the critical paths and control points of the project so that delays do not hold up other work
Correct Answer:

Verified
Correct Answer:
Verified