Multiple Choice
Which is a responsibility of a risk owner?
A) Identify risks to the project that might occur in their department
B) Own and authorize the use of the risk budget to fund risk responses
C) Manage, monitor and control all aspects of an assigned risk
D) Determine project risk appetite
Correct Answer:

Verified
Correct Answer:
Verified