Which statement applies to Stage Plans?
A) Always have the same duration as the Project Plan
B) Are produced at the same time as the Project Initiation Documentation
C) Assist the Project Manager in the day-to-day running and control of the project
D) Provide a baseline against which the Project Board monitor overall progress