Which of the Following Describes Risk Proximity

Question 359

Multiple Choice

Which of the following describes risk proximity?


A) The timeframe over which the risk mitigation actions should be implemented
B) The schedule for the risk management activities related to a plan
C) The timeframe over which a risk will be monitored by the risk owner
D) The timeframe for when the risk might materialize

Correct Answer: