Multiple Choice
A user story was estimated at five ideal hours. On a normal eight hour working day, the team gets about four hours of actual work time. What would be the elapsed time required to complete the Story?
A) One day and two hours
B) Two days
C) Five hours
Correct Answer:

Verified
Correct Answer:
Verified