Multiple Choice
For a Sprint, progress is monitored in a burn-up chart with bars. What makes the bar become longer?
A) The progression of time.
B) Work is added to the Sprint Backlog.
C) Work is deleted from the Sprint Backlog.
Correct Answer:

Verified
Correct Answer:
Verified