Multiple Choice
Why are estimates expressed in terms of story points difficult to explain outside of the team?
A) It requires a comparison to a benchmark, which typically varies from team to team.
B) It requires a deeper understanding of the technical approach to implement each story.
C) It requires breaking the stories down into Sprint Backlog Items, which only the team can do.
Correct Answer:

Verified
Correct Answer:
Verified