Solved

Tasks A, B, and C Have a Duration of Two

Question 321

Multiple Choice

Tasks A, B, and C have a duration of two days. Task D has a duration of three days, and Task E has duration of four days. Task A starts on Day 1, and Task B starts on Day 2. Task C starts after Task A. Tasks D and E start after Task C. Which of the following is the critical path if Task B starts on Day 3?


A) A, C, D
B) A, C, E
C) A, D, E
D) B, C, E

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions