Multiple Choice
During the execution phase of a project, a project task has run longer than anticipated. Which of the following is the new critical path of the project if Task 2 requires an additional two days to complete?
A) 12 days
B) 14 days
C) 16 days
D) 19 days
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q447: While working on risk ranking, the project
Q448: A project is coming to the end
Q449: A software upgrade project has been postponed
Q450: A project team is working on a
Q451: A functional manager within a project is
Q453: Project status meetings have poor attendance. A
Q454: In a Scrum retrospective, which of the
Q455: A project manager noted there were many
Q456: A project is coming to the end
Q457: A PM is reviewing bids from vendors