Multiple Choice
A project manager noted there were many possible features that could be incorporated into a project, and the customers wavered about whether to include particular features. Which of the following is the BEST approach to ensure appropriate delivery of the project?
A) In one section of the project charter, specify which features are included in the project, in another section, specify which features are not included in the project.
B) The scope statement should enumerate which features are included in the project and which features are not included in the project.
C) At the beginning and end of every meeting, the project manager should consistently remind the project team which features are included in the project and which features are not included in the project.
D) The project requirements document lists all the features that are included in the project, and the project manager diligently ensures that features not included in the project are not included in the MOU with the customer.
Correct Answer:

Verified
Correct Answer:
Verified
Q450: A project team is working on a
Q451: A functional manager within a project is
Q452: During the execution phase of a project,
Q453: Project status meetings have poor attendance. A
Q454: In a Scrum retrospective, which of the
Q456: A project is coming to the end
Q457: A PM is reviewing bids from vendors
Q458: Which of the following are characteristics of
Q459: Which of the following is a characteristics
Q460: A project sponsor is reviewing the project