While working on risk ranking, the project team is unsure about the qualitative scales to be used for probability and impact. The project manager directs the team to look in the:
A) quality plan.
B) project management plan.
C) risk register.
D) process diagram.
Correct Answer:

Verified
Correct Answer:
Verified