Multiple Choice
A new project sponsor has joined the project team, and the constraints on the project have been reprioritized. The project cost was previously the most important factor, but the new sponsor has indicated that meeting a new, shorter deadline is the priority. Which of the following effects is this MOST likely to have on the project?
A) The deliverables and quality will remain the same, but the cost will increase.
B) The deliverables and quality will remain the same, but the cost will decrease.
C) The deliverables and cost will remain the same, but the quality will increase.
D) The cost and quality will remain the same, but the deliverables will increase.
Correct Answer:

Verified
Correct Answer:
Verified
Q91: A PM is asked to keep the
Q92: Which of the following is the primary
Q93: While planning a project, the project team
Q94: Expenditure tracking helps with cost:<br>A) reporting<br>B) scheduling<br>C)
Q95: The PMO has asked the PM to
Q97: A project manager needs to track the
Q98: Two team members completely disagree on how
Q99: A highly skilled, key project team member
Q100: Which of the following risk strategies prevents
Q101: Which of the following analyses should a