Multiple Choice
The PMO has asked the PM to provide a status report indicating the number of events and activities required to complete a project. Which of the following charts should the PM include in the status report?
A) Gantt chart
B) Scatter chart
C) Run chart
D) Process diagram
Correct Answer:

Verified
Correct Answer:
Verified