Two Team Members Completely Disagree on How to Complete a Specific

Question 98

Multiple Choice

Two team members completely disagree on how to complete a specific task. The project manager observes the conflict but takes no immediate action. Which of the following techniques is the project manager using?


A) Compromising
B) Smoothing
C) Withdrawing
D) Accepting

Correct Answer: