Multiple Choice
Task ID 3 did not start on time, and no work has been accomplished yet. Evaluate the schedule below: Which of the following is MOST likely the cause?
A) Predecessors not properly identified
B) Scope change
C) Retrospective in progress
D) Insufficient resources assigned
Correct Answer:

Verified
Correct Answer:
Verified