Multiple Choice
A client has provided a list of deliverables to include in the project scope. Which of the following will allow the project team to ensure all deliverables are included in the final product while managing scope creep?
A) Requirements traceability matrix
B) Gantt chart
C) SWOT analysis
D) Project charter