Multiple Choice
The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.
A) -80,000
B) -70,000
C) 10,000
D) 120,000
Correct Answer:

Verified
Correct Answer:
Verified