menu-iconExamlexExamLexServices

Discover

Ask a Question
  1. All Topics
  2. Topic
    Certification
  3. Study Set
    Computing Technology Industry Association (CompTIA)
  4. Exam
    Exam 11: CompTIA Project+
  5. Question
    The Design Activity of a Project Has the Following Cost
Solved

The Design Activity of a Project Has the Following Cost

Question 313

Question 313

Multiple Choice

The design activity of a project has the following cost attributes: PV = 100,000 EV = 20,000 AC = 90,000 Based on this scenario, calculate the schedule variance.


A) -80,000
B) -70,000
C) 10,000
D) 120,000

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q308: An approved change was implemented. Which of

Q309: As a project processes, the team appears

Q310: A local company is part of a

Q311: Midway through a project, the building the

Q312: Because of space limitations, there has been

Q314: Which of the following events would MOST

Q315: During the initiation phase, a project manager

Q316: A contract manager is reconciling project invoices

Q317: Which of the following charts is a

Q318: A project has activities on the critical

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines