During the Initiation Phase, a Project Manager Has Asked for a Document

Question 315

Multiple Choice

During the initiation phase, a project manager has asked for a document containing the high-level objectives and goals for a project. Which of the following documents would contain these items?


A) Business case
B) Requirements document
C) Project timeline
D) Task plan