Multiple Choice
Because of space limitations, there has been a long history of contention among the team. Which of the following actions can the project manager take that would MOST contribute to a successful project?
A) Ignore the issue.
B) Require staff to focus on deliverables.
C) Replace team members.
D) Hold an open dialogue to build consensus.
Correct Answer:

Verified
Correct Answer: