Multiple Choice
Ann, one of the affected stakeholders, feels that the project team has not been giving periodic stakeholder updates and that her input has not been taken into account. Which of the following should the project manager do to ensure stakeholder expectations are met?
A) Ensure that Ann is involved during the testing phase of the project so she can call out functional gaps.
B) Organize a walkthrough of the solution and ensure face-to-face updates occur every two weeks.
C) Escalate the issue to the project steering committee that Ann is criticizing the project quality.
D) Organize a requirements workshop to capture any gaps.
Correct Answer:

Verified
Correct Answer:
Verified
Q199: A small company has a successful proof
Q200: The project team is distributed throughout a
Q201: A sponsor requests that the project team
Q202: A project is running behind schedule. To
Q203: A project manager, who previously worked at
Q205: A project manager is justifying a required
Q206: A project team has completed a major
Q207: A project manager is assigned to a
Q208: A project manager has set aside a
Q209: A project manager is required to maintain