A Project Is Running Behind Schedule

Question 202

Multiple Choice

A project is running behind schedule. To meet the delivery timelines, the project manager decides to give part of the work to another organization for quicker delivery and to allow the project team to focus on the remaining tasks. This is an example of:


A) crashing.
B) outsourcing.
C) task reassignment.
D) relocation.