A Project Team Completed a Brainstorming Activity to Determine Potential

Question 369

Multiple Choice

A project team completed a brainstorming activity to determine potential issues with a project. Which of the following activities should the project team do NEXT?


A) Risk identification
B) Risk quantification
C) Risk planning
D) Risk response

Correct Answer: