Multiple Choice
Despite receiving regular updates, a sponsor learns a project recently slipped. Which of the following documents can the sponsor review to determine the project's performance? (Choose two.)
A) Status report
B) Communication plan
C) Issue log
D) Project schedule
E) Action items list
F) Risk register
Correct Answer:

Verified
Correct Answer:
Verified