Multiple Choice
After identifying all known tasks, the project manager has started to sequence and set durations. Which of the following describes how the project manager should BEST determine the initial sequence and durations?
A) Use milestones identified in the project charter.
B) Use data based on past knowledge.
C) Hold a full team workshop to review the complete WBS.
D) Collaborate with other project managers.
Correct Answer:

Verified
Correct Answer:
Verified
Q360: A team member was replaced on a
Q361: A department manager asks a project manager
Q362: A client has requested a project be
Q363: A project team has just finished one
Q364: Despite receiving regular updates, a sponsor learns
Q366: Which of the following events would MOST
Q367: A project has fallen behind schedule. Upon
Q368: A project manager is implementing a new
Q369: A project team completed a brainstorming activity
Q370: A company has hired a new project