Multiple Choice
A project team started work on a project and was ahead of schedule when the project sponsor announced that the project needed to stop because of shifting strategic priorities. The constraint described in this scenario is:
A) cost
B) environmental
C) scope
D) scheduling
Correct Answer:

Verified
Correct Answer:
Verified