Project B Cannot Start Before Project a Is Complete, but Project

Question 245

Multiple Choice

Project B cannot start before Project A is complete, but Project B has been given authorization to begin to meet legislative requirements. Which of the following is the BEST way to expedite the projects?


A) Project A can reduce the number of deliverables.
B) Project A can be crashed using Project B's resources.
C) Project B can have its resources leveled.
D) Project B can begin without Project A completing, therefore accepting future rework.

Correct Answer: