Multiple Choice
A project manager has updated the risk register with the current risk status, probability, and impact. Risk IDs 2 and 6 have now been realized. Which of the following is the NEXT appropriate step for the project manager to take?
A) Identify risk strategies for the realized events
B) Change the risk status to closed for 2 and 6
C) Consult the risk management plan
D) Update the issue log
Correct Answer:

Verified
Correct Answer:
Verified
Q237: An organization has determined that all projects
Q238: The vendor management team has requested all
Q239: Which of the following conflict resolution techniques
Q240: A project team started work on a
Q241: During a project, a key stakeholder asks
Q243: A company recently went through a project
Q244: A stakeholder is unaware of a project's
Q245: Project B cannot start before Project A
Q246: One deliverable failed during testing, and this
Q247: Upon assignment to a project, the project