Question 24

Question 24

Multiple Choice

Based on the table below: Based on the table below:   Which of the following is the critical path if Task B has extended to ten days? A)  21 days B)  23 days C)  24 days D)  26 days Which of the following is the critical path if Task B has extended to ten days?


A) 21 days
B) 23 days
C) 24 days
D) 26 days

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions

Q19: A project manager recently joined a projectized

Q20: During the storming stage of a project

Q21: A project sponsor has requested documentation to

Q22: An outsourced project team member approaches the

Q23: Which of the following documents does a

Q25: Which of the following activity sequencing techniques

Q26: A key stakeholder asks the project manager

Q27: Which of the following is the first

Q28: A new high-priority project is assigned to

Q29: Which of the following network scheduling techniques

Examlex

ExamLex

About UsContact UsPerks CenterHomeschoolingTest Prep

Work With Us

Campus RepresentativeInfluencers

Links

FaqPricingChrome Extension

Download The App

Get App StoreGet Google Play

Policies

Privacy PolicyTerms of ServiceHonor CodeCommunity Guidelines

Scan To Download

qr-code

Copyright © (2025) ExamLex LLC.

Privacy PolicyTerms Of ServiceHonor CodeCommunity Guidelines