Multiple Choice
An outsourced project team member approaches the project manager and complains that the contract does not permit overtime. The project manager had fast-tracked tasks that require additional hours. Which of the following documents did the project manager fail to reference?
A) MOU
B) MOA
C) SOW
D) SLA
Correct Answer:

Verified
Correct Answer:
Verified