Which of the following activity sequencing techniques uses nodes to symbolize activities and arrows to show how their dependencies are connected?
A) Critical Path Method
B) Arrow Diagramming Method
C) Critical Chain Method
D) Precedence Diagramming Method
Correct Answer:

Verified
Correct Answer: