If a project sponsor wants to know the current status and progress of a project, which of the following is the BEST approach to find this information?
A) The project sponsor should obtain the current status from team members, put it into a presentation, and present it to the project manager for review.
B) The scheduler should obtain the current status from team members, apply it to the baseline of the schedule, and run a report.
C) The scheduler should obtain the current status from team members, update the project charter, project management plan, dashboard, and SOW, and then create a status report to provide to the project manager.
D) The scheduler should obtain the current status from team members, update the risk register, and provide the information to the project champion for review.
Correct Answer:

Verified
Correct Answer:
Verified
Q55: A project manager is collecting the number
Q56: A customer will have ongoing changes to
Q57: Task ID 3 did not start on
Q58: A project is nearing the expected completion
Q59: A stakeholder wants to add four more
Q61: Tasks B and D start after Task
Q62: Which of the following risk strategies is
Q63: ? new stakeholder has been added to
Q64: Tasks A and B have a duration
Q65: Which of the following will identify the