Multiple Choice
A project is nearing the expected completion date, but it is behind schedule. The project manager has decided to fast-track the resources. Which of the following impacts will MOST likely occur? (Choose two.)
A) Cost will increase.
B) Scope will increase.
C) Schedule will decrease.
D) Risk will decrease.
E) Budget will increase.
F) Quality will increase.
Correct Answer:

Verified
Correct Answer:
Verified
Q53: Which of the following organizational structures uses
Q54: A project team is identifying, rating the
Q55: A project manager is collecting the number
Q56: A customer will have ongoing changes to
Q57: Task ID 3 did not start on
Q59: A stakeholder wants to add four more
Q60: If a project sponsor wants to know
Q61: Tasks B and D start after Task
Q62: Which of the following risk strategies is
Q63: ? new stakeholder has been added to