A company decides to give a large section of its development project to another firm to manage and complete because that firm has the appropriately skilled resources to execute the work. This approach is referred to as:
A) Resource leveling
B) Staff Augmentation
C) Work relocation
D) Outsourcing
Correct Answer:

Verified