Multiple Choice
A project manager is assigned to an ongoing project. Which of the following is the FIRST document the protect manager should review?
A) Project schedule
B) Action items
C) Project charter
D) Communication plan
Correct Answer:

Verified
Correct Answer:
Verified
Related Questions
Q30: A company decides to give a large
Q31: Which of the following project phases occurs
Q32: A team member was assigned a new
Q33: A diagram or chart is required to
Q34: A company was originally organized using a
Q36: The project team has identified all the
Q37: A vendor is late with product deliverables.
Q38: The government wants to start a project
Q39: The internal project sponsor is frustrated by
Q40: A project encountered a problem and reached