A Department Manager Asks a Project Manager About the Status

Question 361

Multiple Choice

A department manager asks a project manager about the status of a project that has only a few employees from the department assigned to it. Which of the following were MOST likely missed during project planning?


A) Issue log and process diagram
B) Resource analysis and Gantt chart
C) Stakeholder analysis and communication plan
D) Scatter chart and scope analysis

Correct Answer: