Multiple Choice
A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?
A) Add durations.
B) Add the start and finish dates
C) Add tasks.
D) Add resources.
Correct Answer:

Verified
Correct Answer:
Verified
Q431: A key team member found a new
Q432: A project team received a memo stating
Q433: Based on the table below: <img src="https://d2lvgg3v3hfg70.cloudfront.net/C1257/.jpg"
Q434: Which of the following roles has approval
Q435: An engineer is troubleshooting a malfunctioning physical
Q437: A project team is creating a new
Q438: A primary work location is unsafe due
Q439: Which of the following BEST describes the
Q440: A company's management team is in a
Q441: The managing director of a law firm