A Governance Committee Has Just Approved a New Project

Question 436

Multiple Choice

A governance committee has just approved a new project. The project scheduler is now developing the project schedule. Which of the following activities should be done FIRST?


A) Add durations.
B) Add the start and finish dates
C) Add tasks.
D) Add resources.

Correct Answer:

verifed

Verified