Question 440

Multiple Choice

A company's management team is in a meeting to review all the products and services delivered in the first quarter of the year for profitability. They are requesting information on payback period, return on investment, and total cost of ownership. The project manager is checking the project repository for available documentation. In which of the following documents is the project manager MOST likely to find the required information?


A) Business case
B) Project charter
C) Risk management plan
D) Scope of work