Multiple Choice
Two critical members have approached the project manager separately regarding personality conflicts. The project manager cannot remove either from the project or separate their work activities. To help resolve the conflict, which of the following would be BEST for the project manager to do?
A) Send an email to the entire project team encouraging proper etiquette.
B) Discuss the problem during the next daily status update.
C) Perform an in-person meeting involving both parties.
D) Schedule a mandatory team-building activity.
Correct Answer:

Verified
Correct Answer:
Verified
Q79: A project team is composed of numerous
Q80: A task on the critical path will
Q81: A Scrum team is completing a sprint;
Q82: A senior manager asks a project manager
Q83: A project manager wants to introduce the
Q85: Which of the following are the BEST
Q86: Two companies have merged. Which of the
Q87: Which of the following measurements would give
Q88: Which of the following communication methods and
Q89: The project's network map has a loop