Multiple Choice
A Scrum team is completing a sprint; however, some tasks will need to carry over to the next sprint. Which of the following should the Scrum master do to improve the team's velocity in the next sprint?
A) Take a more hands-on leadership approach.
B) Add the unfinished work to the backlog.
C) Schedule a sprint retrospective.
D) Hold additional daily stand-up meetings.
Correct Answer:

Verified