Multiple Choice
A task on the critical path will not be completed on time. The project manager is reviewing both the schedule and the risk register to create a corrective action plan. The project completion date and quality of the deliverable cannot change. Which of the following activities should the project manager perform NEXT?
A) Revise the project plan.
B) Update the issue log.
C) Request additional funding.
D) Issue a change request.