Joe, a Stakeholder, Threatens to Withdraw from a Project That

Question 445

Multiple Choice

Joe, a stakeholder, threatens to withdraw from a project that is not going according to his wishes. The president talks to the project manager regarding options for a response to the stakeholder, and they decide the project will move forward as originally planned. Which of the following risk strategies was used?


A) Accept
B) Mitigate
C) Avoid
D) Transfer