Solved

In the Review of a Project Status Report, the Slack

Question 462

Multiple Choice

In the review of a project status report, the slack is negative. Which of the following should the project manager tell the stakeholders?


A) The project is behind schedule
B) The project is over budget
C) The project has float available
D) The project needs a gate review

Correct Answer:

verifed

Verified

Unlock this answer now
Get Access to more Verified Answers free of charge

Related Questions