Multiple Choice
A project sponsor is reviewing the project dashboard and does not understand what a CPI of 0.87 and an SPI of 1.02 indicate. Which of the following describes the project status?
A) The project is over budget and behind schedule.
B) The project is under budget and ahead of schedule.
C) The project is over budget and ahead of schedule.
D) The project is under budget and behind schedule.
Correct Answer:

Verified
Correct Answer:
Verified
Q455: A project manager noted there were many
Q456: A project is coming to the end
Q457: A PM is reviewing bids from vendors
Q458: Which of the following are characteristics of
Q459: Which of the following is a characteristics
Q461: Project A is delivering the foundation for
Q462: In the review of a project status
Q463: A project manager has developed the initial
Q464: Which of the following are major characteristics
Q465: Three IT companies have agreed to summarize