Multiple Choice
Project A is delivering the foundation for Project B. Construction regulations have changed during Project A, requiring work to be redone in the allocated buffer. Which of the following is the MOST likely impact to Project B?
A) The cost will increase.
B) There will be no impact.
C) The scope will change.
D) The schedule will change.
Correct Answer:

Verified
Correct Answer:
Verified
Q456: A project is coming to the end
Q457: A PM is reviewing bids from vendors
Q458: Which of the following are characteristics of
Q459: Which of the following is a characteristics
Q460: A project sponsor is reviewing the project
Q462: In the review of a project status
Q463: A project manager has developed the initial
Q464: Which of the following are major characteristics
Q465: Three IT companies have agreed to summarize
Q466: A project manager is assigned to a