Multiple Choice
Upon assignment to a project, the project manager is given a set budget, a due date, and a clearly defined description of desired deliverables. Which of the following should the project manager do NEXT?
A) Determine the flexibility between the project constraints
B) Hold a kick-off meeting with the project team
C) Determine procurement needs to meet the project demands
D) Create the risk register
Correct Answer:

Verified
Correct Answer:
Verified