Multiple Choice
A key stakeholder claims to have not received status updates per the agreement. The PM reviews the communications plan and determines the updates were provided as agreed upon. Which of the following should the PM do NEXT to resolve the inconsistency between the communications plan and the stakeholder's expectations?
A) Analyze the RASI chart
B) Review previous meeting minutes.
C) Initiate a change control request.
D) Updates the communications plan.
Correct Answer:

Verified
Correct Answer:
Verified