A Project Manager Has Gathered Time Estimates for a New

Question 198

Multiple Choice

A project manager has gathered time estimates for a new project's activities and is now ready to begin developing the schedule. Which of the following would the project manager most likely do NEXT?


A) Create a WBS.
B) Determine predecessors and dependencies.
C) Determine the critical path.
D) Prioritize tasks.

Correct Answer: