A firm, fixed-price project is on pace to exceed the maximum defect rate identified in the project charter. The customer has stated the project must be delivered on time. Which of the following is the BEST option for the project to complete on time and within parameters?
A) Reduce the project scope.
B) Crash the schedule.
C) Request additional budget from the customer.
D) Apply new resources to the project.