Multiple Choice
A project manager is performing resource leveling and notices one of the functional testers is assigned 40% in a second project. The project manager needs the resource to be 100% dedicated to the project; otherwise, the testing phase jeopardizes the delivery date. Which of the following should the project manager do NEXT?
A) Ask the resource manager to deallocate the resource from the second project.
B) Ask the resource manager to assign a new resource with 40% of allocation.
C) Keep the resource 100% allocated in the project, as per the initial plan.
D) Change the resource to 60% of allocation and review the mitigation plan.
Correct Answer:

Verified
Correct Answer:
Verified
Q39: The internal project sponsor is frustrated by
Q40: A project encountered a problem and reached
Q41: A company hires a number of interns
Q42: A company purchased a parachute supplier and
Q43: Which of the following is a reason
Q45: Assuming an iterative approach, which of the
Q46: Which of the following documents is a
Q47: The project team is not comfortable moving
Q48: A project manager at a projectized organization
Q49: A customer has stated that meeting the